Laying construction
1 Preparation
First of all, planning and measurement should be carried out to ensure a certain slope, so that the water can flow smoothly from the upper end to the lower end; second, after the construction site is cleaned and leveled, the construction line is set according to the design drawing, and the drainage slope is retested.
2 excavation
The construction line shall be set up according to the design requirements, both sides of the ditch shall be leveled, and there shall be no empty soil and cavity on the slope surface of the ditch. To tamp the water damaged parts, in addition to the debris and gravel in the slope, if necessary, use Panax notoginseng lime soil compaction treatment, or grouting reinforcement after sealing, which requires that the treated parts have good stability!
3 laying
The material can be laid vertically and horizontally. Please make sure that the base is smooth, otherwise it will affect the appearance quality!
4 joint treatment
1. A pit with a width of 10 cm and a depth of twice that of the cement blanket shall be excavated horizontally at the overlapping position of two adjacent cement blankets,
Place and flatten the cement blanket joint at the overlap.
2. Press the upper cement blanket on the lower cement blanket along the water flow direction, and the superposition position shall not be less than
10cm。
3. Apply sealant evenly at the joint.
4. Fix two pieces of cement blanket with Φ 5 * 38mm stainless steel screws.
5 ditch edge treatment
Fix the edge of the material on the edge of the ditch with rivets, and fix the overlapped part with rivets. After fixing, cover the edge with soil
6 water curing
Before watering, it is necessary to check and accept the whole laying before watering. Watering can only be carried out after it is qualified! Water 9kg per square meter (the thickness is calculated as 10mm) should be thoroughly watered. It should not be watered less and evenly from the edge to the middle
Spray water, the best way is spraying, the flow rate is 4000ml / min, until the color of cement blanket becomes dark. Do not use high pressure water column! When the temperature is less than or equal to 5 ℃, insulation measures shall be taken; when the average temperature of day and night is higher than 30 ℃, the surface shall be covered with plastic film or geotextile and other materials to keep it moist, and the watering curing time shall not be less than 3 days
Quality acceptance methods and standards
general provisions
1.1 when the average day and night temperature of the construction site is lower than 5 ℃ or the minimum temperature is lower than 0 ℃ for 5 consecutive days, it is necessary to enter the winter construction.
1.2 when the material strength does not reach 60% of the design strength, it shall not be frozen. When the material begins to freeze under the condition of water immersion and freeze-thaw, it shall not be less than 80% of the design strength
Inspection items
2.1. Before laying the composite blanket, the base shall be fully compacted. The simple measurement method is: use a Φ 12mm steel drill rod, use 30kg pressure, and insert into the soil less than 5cm.
Inspection quantity: spot check
Test method: observation and measurement with tools.
2.2. The ditch bottom and side shall be flat; the deviation of ditch section size shall not exceed 5cm. Base leveling treatment, after laying the composite blanket, the flatness is required to be measured with 3M chord rope, and the average loss is not more than 20mm.
Inspection quantity: spot check
Inspection method: observation and measurement with steel ruler.
2.3. The anchor spacing error is required to be ± 5cm; the construction error of screw spacing is ± 2cm. No less nails or missing nails are allowed, and the nails are firmly fixed.
Inspection quantity: total inspection
Inspection method: observation and measurement with steel ruler.
2.4 water the blanket evenly and thoroughly until the color of blanket becomes darker. No less than 9kg per square meter (calculated by 10 mm thick blanket), no less watering. More watering will not affect the quality of the project.
2.5. The slurry should be uniform and the thickness should be uniform. The mass ratio of cement to water should be 1:3 ~ 1:4. There should be no missing or less brushing. Eight
Inspection quantity: spot check
Test method: observation.
2.6. The PVC drain pipe of drainage hole shall be arranged in the form of 2m × 2m plum blossom, which shall not be omitted and installed firmly.
Inspection quantity: total inspection
Inspection method: observation and measurement with steel ruler.
2.7. The reserved size of end face shall meet the requirements: 1-2m width of slope length is reserved at the top of slope, and 50cm of reserved length of bottom surface.
Inspection quantity: total inspection
Inspection method: observation and measurement with steel ruler.
2.8. The laying and installation of materials shall comply with the requirements of construction design, and shall be stable and reliable, with tight joints, smooth and beautiful appearance.
Inspection quantity: total inspection
Inspection method: observation and measurement with steel ruler.